Blog Posts Process Management

Managing dependencies with leads and lags in project management

Blog: Monday Project Management Blog

Lead and lag are scheduling techniques used with task relationships like Finish-to-Start and Start-to-Start when managing project dependencies. Project managers use lead and lag time when creating project schedules to ensure that activities are completed efficiently and effectively.

In this guide, we’ll answer some common questions related to leads and lags in project management, share some tips for managing leads and lags in projects, and show you how monday work management can help manage leads and lags efficiently.

Get started

What’s the difference between leads and lags in project management?

Lead and lag are the terms used to define a relationship between project tasks.

A lead defines the overlap between dependent items, such as project tasks or phases. It’s the amount of time in which a predecessor activity can begin in parallel with a successor activity — i.e. there are no constraints or conditions before commencing the successor activity.

A lag signifies the delay between dependent items, such as the end of one project task and the beginning of another. It’s the amount of time that must elapse between a successor activity and a predecessor activity — i.e. there are constraints or conditions before commencing the successor activity.

In project management software, the subtraction symbol represents leads because they overlap activities to shorten project duration. While the plus sign represents lags as they delay activities and add time to the project duration.

Key terms to understand about leads and lags

Two key terms to understand when discussing leads and lags in project management are predecessor and successor.

A predecessor is an activity that must be completed before another activity can start or finish — i.e. it’s a task that potentially prevents other tasks from starting or ending.

On the other hand, a successor is an activity that follows another activity — i.e. it’s a task waiting on other tasks to start or finish.

What’s the difference between lead time vs. lag time in projects?

Lead and lag time are two project management terms used with task dependency relationships: Finish to Start, Start to Start, Finish to Finish, and Start to Finish.

Lead time refers to the amount of time that you can advance a successor activity relative to a predecessor activity. For example, if Activity A takes 5 days to complete and Activity B has a lead time of 2 days, then Activity B can start 2 days before Activity A finishes.

On the other hand, lag time refers to the amount of time that you must delay a successor activity relative to a predecessor activity. For example, if Activity B has a lag time of 2 days, then it can start only 2 days after Activity A finishes.

Here’s a video explaining the difference between lead time and lag time.

What are leads and lags used for in project management?

Project managers use leads and lags to identify necessary delays and plan for timesaving opportunities.

For example, they use leads to:

Whereas they use lags to:

Leads and lags can help managers sequence activities logically within a more extensive project timeline, create project schedules, and complete projects on time and within budget.

What’s an example of lead and lag in project management?

Here’s an example of using lead and lag in project management.

Lead example:

At monday.com, there is a 2-day overlap between starting to develop a feature (Activity B) and finishing its design (Activity A) — i.e. there’s a lead of 2 days.

Lag example:

In a construction project, there’s a 2-day delay required between finishing the plastering (Activity A) and starting the painting (Activity B) to allow the walls to dry — i.e. there’s a lag of 2 days.

What are the benefits of managing leads and lags efficiently?

Managing leads and lags efficiently allows project managers to improve project monitoring, save time, reduce risks, evaluate performance, and complete projects on time.

  1. Improve project monitoring. By managing leads and lags efficiently, project managers can monitor the activities of a project and ensure that they are progressing as planned.
  2. Reduce project duration. Being aware of the leads and lags of activities can help project managers save time. Project managers can reduce the overall project duration by using lead time to draw activities closer to the project’s start date.
  3. Mitigate risks. Project managers can use leads and lags to create buffer time between activities and tasks, which can help manage risks. Buffer time can also be used as a contingency to account for unexpected delays or to allow for some flexibility in the schedule.
  4. Evaluate performance. Lead and lag indicators in project management help evaluate performance. By comparing lead and lag indicators, you can analyze previous projects and see where you performed optimally and where you can improve.
  5. Achieve project completion time. By managing leads and lags efficiently, project managers can calculate project timeline variations to ensure the project finishes within the planned time frame.

Tips for managing leads and lags in projects

Here are some tips for managing leads and lags in projects:

Example of a Finish-to-Start (FS) with a lead of 2 days on monday.com
Get started

How monday.com can help you manage leads and lags

At monday.com, we understand the importance of managing projects with strict timelines — that’s why our work management platform includes the tools to help you manage them.

On your project board, you can edit task durations and adjust the lead and lag time to create overlaps and gaps accordingly. Shifting things around while keeping dependent tasks aligned gives you fantastic flexibility throughout a project.

You can accomplish all this with one magic column…

The Dependency Column

On monday work management, you can use the “lead and lag” feature to define any necessary delays or opportunities to save time in a project plan right from the Dependency Column.

Selecting the Dependency Column on monday.com

Once you’ve added the Dependency Column, you can choose the mode in which your dependencies will work — Flexible, Strict, or No action. But if you want to use leads and lags to define any necessary delays or overlaps, you’ll need to select the Strict dependency mode.

Select 'Strict' dependency mode on monday.com

You’ll also need to choose the time column on which your items depend — Date Column or Timeline Column.

Choose the time column — Date Column or Timeline Column — on which your items depend on monday.com

As you set up the dependencies between the items on your board, you can select the dependency type for each individual relationship — from Finish-to-start, Start-to-start, Finish-to-finish, and Start-to-finish — and then add your lead or lag.

Example of adding lag to a Finish-to-Start dependency on monday.com

Adding a lead to a dependency

For example, you might have a Finish-to-Start (FS) with a lead of 2 days, indicated with a negative (-) symbol:

Example of a Finish-to-Start (FS) with a lead of 2 days on monday.com

In the Gantt chart, an overlap displays between the dependent tasks, and as you move one item, the dependent tasks move in sync accordingly:

Example of a lead on a Gantt chart with an overlap between the dependent tasks on monday.com

Adding a lag to a dependency

For example, you might have a Finish-to-Start (FS) with a lag of 2 days, indicated with a positive number:

Example of a Finish-to-Start (FS) with a lag of 2 days on monday.com

In the Gantt chart, a gap displays between the dependent tasks, and as you move one item, the dependent tasks move in sync accordingly:

Example of lag on a Gantt chart showing a gap between the dependent tasks on monday.com

Overall, the Dependency Column makes managing project leads and lags for each dependency relationship effortless!

** Note: This column is available on our Pro and Enterprise plans.

Get started

Control lead and lag time with a robust work management platform

Managing dependencies with leads and lags is one of the most critical activities in project management as it saves time, reduces risks, and ensures projects complete on time and within budget.

With monday work management — built upon the robust monday.com Work OS — you can visually organize, plan, and track every task-dependent lead and lag time in a few clicks.

FAQs about leads and lags

A lead defines the overlap between dependent items, such as project tasks or phases. It’s the amount of time in which a predecessor activity can begin in parallel with a successor activity — i.e. there are no constraints or conditions before commencing the successor activity. 
A lag signifies the delay between dependent items, such as the end of one project task and the beginning of another. It’s the amount of time that must elapse between a successor activity and a predecessor activity — i.e. there are constraints or conditions before commencing the successor activity. 

Lead time refers to the amount of time that you can advance a successor activity relative to a predecessor activity. For example, if Activity A takes 5 days to complete and Activity B has a lead time of 2 days, then Activity B can start 2 days before Activity A finishes.
On the other hand, lag time refers to the amount of time that you must delay a successor activity relative to a predecessor activity. For example, if Activity B has a lag time of 2 days, then it can start only 2 days after Activity A finishes.

Project managers use leads and lags to identify necessary delays and plan for timesaving opportunities.
For example, they use leads to:
* Measure how long it will take to complete a task or project phase.
* Identify opportunities to reduce the total duration of a project.
* Evaluate performance by comparing lead indicators to lag indicators.
Whereas they use lags to:
* Measure how far behind a task or project phase is after it has started.
* Schedule activities that cannot be started until another activity has been completed.
* Account for downtime between two tasks due to unforeseen incidents or accidents.
Leads and lags can help managers sequence activities logically within a more extensive project timeline, create project schedules, and complete projects on time and within budget.

Here’s an example of using lead and lag in project management.
Lead example:
At monday.com, there is a 2-day overlap between starting to develop a feature (Activity B) and finishing its design (Activity A) — i.e. there’s a lead of 2 days.
Lag example:
In a construction project, there’s a 2-day delay required between finishing the plastering (Activity A) and starting the painting (Activity B) to allow the walls to dry — i.e. there’s a lag of 2 days.

Managing leads and lags efficiently allows project managers to improve project monitoring, save time, reduce risks, evaluate performance, and complete projects on time.
* Improve project monitoring. By managing leads and lags efficiently, project managers can monitor the activities of a project and ensure that they are progressing as planned.
* Reduce project duration. Being aware of the leads and lags of activities can help project managers save time. Project managers can reduce the overall project duration by using lead time to draw activities closer to the project’s start date.
* Mitigate risks. Project managers can use leads and lags to create buffer time between activities and tasks, which can help manage risks. Buffer time can also be used as a contingency to account for unexpected delays or to allow for some flexibility in the schedule.
* Evaluate performance. Lead and lag indicators in project management help evaluate performance. By comparing lead and lag indicators, you can analyze previous projects and see where you performed optimally and where you can improve.
* Achieve project completion time. By managing leads and lags efficiently, project managers can calculate project timeline variations to ensure the project finishes within the planned time frame.

{
“@context”: “https://schema.org”,
“@type”: “FAQPage”,
“mainEntity”: [
{
“@type”: “Question”,
“name”: “What’s the difference between leads and lags in project management?”,
“acceptedAnswer”: {
“@type”: “Answer”,
“text”: “

A lead defines the overlap between dependent items, such as project tasks or phases. Itu2019s the amount of time in which a predecessor activity can begin in parallel with a successor activity u2014 i.e. there are no constraints or conditions before commencing the successor activity.u00a0
nA lag signifies the delay between dependent items, such as the end of one project task and the beginning of another. Itu2019s the amount of time that must elapse between a successor activity and a predecessor activity u2014 i.e. there are constraints or conditions before commencing the successor activity.u00a0

n”
}
},
{
“@type”: “Question”,
“name”: “Whatu2019s the difference between lead time vs. lag time in projects?”,
“acceptedAnswer”: {
“@type”: “Answer”,
“text”: “

Lead time refers to the amount of time that you can advance a successor activity relative to a predecessor activity. For example, if Activity A takes 5 days to complete and Activity B has a lead time of 2 days, then Activity B can start 2 days before Activity A finishes.
nOn the other hand, lag time refers to the amount of time that you must delay a successor activity relative to a predecessor activity. For example, if Activity B has a lag time of 2 days, then it can start only 2 days after Activity A finishes.

n”
}
},
{
“@type”: “Question”,
“name”: “What are leads and lags used for in project management?u00a0”,
“acceptedAnswer”: {
“@type”: “Answer”,
“text”: “

Project managers use leads and lags to identify necessary delays and plan for timesaving opportunities.
nFor example, they use leads to:
n* Measure how long it will take to complete a task or project phase.
n* Identify opportunities to reduce the total duration of a project.
n* Evaluate performance by comparing lead indicators to lag indicators.
nWhereas they use lags to:
n* Measure how far behind a task or project phase is after it has started.
n* Schedule activities that cannot be started until another activity has been completed.
n* Account for downtime between two tasks due to unforeseen incidents or accidents.
nLeads and lags can help managers sequence activities logically within a more extensive project timeline, create project schedules, and complete projects on time and within budget.

n”
}
},
{
“@type”: “Question”,
“name”: “Whatu2019s an example of lead and lag in project management?”,
“acceptedAnswer”: {
“@type”: “Answer”,
“text”: “

Hereu2019s an example of using lead and lag in project management.
nLead example:
nAt monday.com, there is a 2-day overlap between starting to develop a feature (Activity B) and finishing its design (Activity A) u2014 i.e. thereu2019s a lead of 2 days.
nLag example:
nIn a construction project, thereu2019s a 2-day delay required between finishing the plastering (Activity A) and starting the painting (Activity B) to allow the walls to dry u2014 i.e. thereu2019s a lag of 2 days.

n”
}
},
{
“@type”: “Question”,
“name”: “What are the benefits of managing leads and lags efficiently?”,
“acceptedAnswer”: {
“@type”: “Answer”,
“text”: “

Managing leads and lags efficiently allows project managers to improve project monitoring, save time, reduce risks, evaluate performance, and complete projects on time.
n* Improve project monitoring. By managing leads and lags efficiently, project managers can monitor the activities of a project and ensure that they are progressing as planned.
n* Reduce project duration. Being aware of the leads and lags of activities can help project managers save time. Project managers can reduce the overall project duration by using lead time to draw activities closer to the projectu2019s start date.
n* Mitigate risks. Project managers can use leads and lags to create buffer time between activities and tasks, which can help manage risks. Buffer time can also be used as a contingency to account for unexpected delays or to allow for some flexibility in the schedule.
n* Evaluate performance. Lead and lag indicators in project management help evaluate performance. By comparing lead and lag indicators, you can analyze previous projects and see where you performed optimally and where you can improve.
n* Achieve project completion time. By managing leads and lags efficiently, project managers can calculate project timeline variations to ensure the project finishes within the planned time frame.

n”
}
}
]
}

The post Managing dependencies with leads and lags in project management appeared first on monday.com Blog.

Leave a Comment

Get the BPI Web Feed

Using the HTML code below, you can display this Business Process Incubator page content with the current filter and sorting inside your web site for FREE.

Copy/Paste this code in your website html code:

<iframe src="https://www.businessprocessincubator.com/content/managing-dependencies-with-leads-and-lags-in-project-management/?feed=html" frameborder="0" scrolling="auto" width="100%" height="700">

Customizing your BPI Web Feed

You can click on the Get the BPI Web Feed link on any of our page to create the best possible feed for your site. Here are a few tips to customize your BPI Web Feed.

Customizing the Content Filter
On any page, you can add filter criteria using the MORE FILTERS interface:

Customizing the Content Filter

Customizing the Content Sorting
Clicking on the sorting options will also change the way your BPI Web Feed will be ordered on your site:

Get the BPI Web Feed

Some integration examples

BPMN.org

XPDL.org

×